Emergency Preparedness FMJ Article
When Disaster Strikes
Scott Baird
The school building has been evacuated, the students have
been sent home and the flames have been extinguished. Now
that the urgency of the fire has died down, it is replaced
by the depressing picture of a burned-out, smoldering building.
Broken glass and yellow police tape strung across the entrance
accentuate the long journey ahead of your organization.
Where is the road to recovery? How can you quickly and
completely recover from a disaster? Although the specific
suggestions in this article are based on fire experiences
in public school buildings, the principles apply equally
to disaster recovery (flood, earthquake, etc.) in diverse
types of facilities.
After the initial problems of evacuation, extinguishing
the fire and crowd control are taken care of, the real work
begins. Since these issues are typically left to emergency
response personnel, I will not address them in this article.
However, once the flames are out, you cannot assume that
you will be allowed access to your facility immediately.
There are at least two types of investigations that must
take place first. Law enforcement officials will investigate
the scene to determine the cause and origin of the fire.
Then, insurance companies representing the owner or companies
implicated in causing the fire will also investigate the
scene. Often, this second investigation is more time-consuming
and comprehensive than the law enforcement investigation.
After you have dealt with the press, emotional parents,
excited students, employees and other building occupants,
your mind will race to whom you should contact next. One
of the first calls that should be placed is to your insurance
carrier. The company will assign an adjuster to your project.
This individual may be an employee of the insurance company
or a private company that contracts adjuster services to
the insurance company.
Your next call should be to a construction management
firm experienced in disaster recovery. This company will
manage the recovery process with you. Your insurance carrier
will pay their professional fee. This will ensure that you
are adequately compensated for the loss and that fire recovery
issues do not put an excessive burden on the building’s
administrative personnel.
The work necessary to return the building to a usable
condition can be divided into two phases. The first phase
is remediation. The second is reconstruction. The first
phase occurs as soon as the owner is permitted back into
the building—after the law enforcement investigation
is complete, but before the insurance investigation is finished.
The purpose of remediation is to seal off the effected portion
of the building, to prevent further damage from occurring
and to eliminate or control any hazards. The reconstruction
phase is a more carefully planned and time-consuming process
that will return the damaged portion of the building to
a usable condition.
Phase 1: Remediation
The goals during this phase are:
1. To eliminate or control hazards;
2. To prevent further damage to the building; and
3. To make unimpaired areas of the building available for
use.
It is critical to expedite this phase. Work should be
done on evenings, weekends, or holidays. The management
team should be prepared to do whatever is necessary to reopen
the building. Good communication is essential between the
insurance adjuster (who will need to approve all expenditures),
the construction manager and the owner. It may be necessary
for the building’s custodial staff to work overtime
during this period to keep the building open and accessible.
These overtime charges can and should be reimbursed by the
insurance carrier.
One of the most important facets of remediation is eliminating
and controlling the hazards that have been caused by the
disaster. This will require licensed, insured contractors
who can install temporary measures. Electricians will be
needed to “safe off” all exposed wires and conduits,
isolate the damaged circuits and restore power where possible.
General construction contractors should remove partially
burned and unsafe doors, roofs, canopies, ceilings, etc.,
which could collapse on future reconstruction or investigation
crews. Of course, this will have to be carefully coordinated
with any ongoing insurance investigation, as the investigators
may require that certain areas not be disturbed. Access
to the reconstruction area should be blocked with temporary
partitions, temporary fencing, etc. Broken glass, sharp
steel and other hazards should be removed. All of this work
should begin immediately after the law enforcement investigation
has ended. The insurance adjuster will be involved with
the price negotiations, but the goal should be to make the
area safe in the quickest possible manner.
The second step in remediation is to prevent further damage
to the building. The primary source of this possible damage
is water. All of the affected roofs should be flood tested
to determine if they are damaged. In a fire situation, the
primary damage roofs typically occurs when emergency workers
cut holes to vent the building or drop axes, pry bars or
other tools on the roof. In addition to the roof, all windows,
skylights and doors should be checked. These should be boarded
up if necessary. Although this work takes place in the quickest
possible manner, it should not be of poor quality. The owner
and contractors should assume that all remediation measures
put in place will be needed for approximately four to six
months. That means that skylights boarded up in July should
be built to withstand a snowfall.
Finally, it is necessary to return as much of the building
as possible to a useable state. When considering the scope
of remedial work, all of the destructive forces should be
considered. For example, after a fire, the remediation scope
should include fire damage, smoke damage and water damage.
It is unacceptable to reoccupy a space that has a strong,
persistent smoke odor or a soot residue on the surfaces.
For this reason, remediation should include a thorough cleaning
of spaces adjacent to the fire damaged area. This includes
furniture, walls, floors, and ceilings. Also, a duct-cleaning
contractor should be hired to clean all affected ductwork,
which may extend into far distant locations in the building.
It may be necessary to paint some of the charred surfaces
with a smoke-sealing primer or install a negative air pressure
system in the fire area to prevent smoke fumes from infiltrating
back into the reoccupied areas. Ozonation machines have
also been used to successfully remove the smoke odor from
areas that are to be reoccupied.
Remediation Checklist
1. Eliminate hazards
- Secure all exposed wires
- Remove damaged doors, ceilings, etc.
- Remove sharp objects (glass, steel, etc)
- Block access to damaged area
2. Prevent further damage
- Test and fix roof
- Board up broken windows/doors
3. Return building to use
- Clean ducts
- Clean adjacent rooms
- Seal burned areas with paint
- Ozone to remove odor
Phase 2: Reconstruction
The reconstruction phase is a more comprehensive, time-consuming
process than remediation. The purpose of this phase is to
completely compensate the owner for the loss. This means
that the owner should have a building that, at the very
minimum, matches the original building or space that was
lost. The two steps in the reconstruction phase are planning
and implementation.
The purpose of the planning step is to establish a scope
of work and have it approved by the responsible parties.
The same rule of thumb that was used in the remediation
phase should also be used in the reconstruction phase. When
deciding the scope of work, remember all of the destructive
forces. In the case of a fire, remember smoke and water
too. Often, after a fire, it is necessary to remove a great
deal of the insulation in the building. Smoke and soot can
move through pipe insulation and be found in an area of
the building some distance from where the fire occurred.
In one fire, the water from the firefighters damaged a transformer,
the floor tile and a wood door and cabinet on the floor
below where the fire occurred.
A licensed architect should prepare the scope, drawings
and any specifications for the reconstruction work. Of course,
the owner and construction manager should assist the architect.
The insurance adjuster, and ultimately the insurance carrier,
will have to approve the scope of work. This should be done
as a preliminary step before detailed construction documents
are prepared. As a preliminary step, a professional structural
engineer should provide a written opinion on the condition
of any structural members that were affected by the fire.
This opinion should be obtained for the protection of the
owner, even if there does not appear to be major damage
to the structural members. The insurance company should
pay all professional fees.
In addition to replacing damaged items, the insurance
coverage held by the owner may allow for “code upgrades.”
For example, in one fire, a wooden entry landing was burned.
The previous landing had four steps, but no handicap access.
The owner’s coverage allowed the replacement structure
to be constructed of concrete instead of wood (in compliance
with modern fire codes) and to include a wheelchair ramp
(in compliance with the Americans with Disabilities Act).
It may be necessary for the completed plans and specifications
to be reviewed by a governing agency. In New York, the State
Education Department has to review the prints and specifications
for conformity with their requirements. This is required
even though the insurance company is funding the reconstruction.
Usually, the governing agency can be persuaded to give priority
attention to the reconstruction documents if they are made
aware of the circumstances.
The decision-making process surrounding the establishment
of a scope of work should take place at a rapid pace. Questions
such as: “Should this piece of equipment be refurbished
or replaced?” must be handled in a decisive manner.
The more time that is allowed to elapse before the decision
is made, the more the tendency will be to just clean or
refurbish the equipment. This will result in the owner getting
less than what is deserved from the insurance settlement.
If the building owner is a public entity (such as a public
school district), the implementation process will be subject
to public bidding protocols. Treating the reconstruction
as a typical project, however, is a mistake. Cooperative,
flexible and skilled contractors are needed to quickly reconstruct
the damaged areas. The public bidding process does not always
bring this level of contractor to the fore. After consultation
with the insurance adjuster, the owner’s attorney
and the construction manager, some adjustments may be possible
to the typical bidding process.
The selected contractor should be required to sign a contract
with the building owner, should provide performance and
payment bonds and should provide appropriate insurance.
It is prudent to specify working hours, completion deadlines
and liquidated damages in the construction documents. These
measures will help ensure that the building owner is protected
and that the reconstruction is performed in a timely manner.
The issue of cash flow should be considered early in the
implementation process. Since the contractors involved will
be providing quick turnaround, they will need swift reimbursement.
Often, the process for procuring money from the insurance
company can be slow and bureaucratic. It may be advantageous
for the insurance carrier to provide an “advance”
to the owner that can be used to pay contractors.To expedite
the decision-making process, regular meetings should be
held with the insurance adjuster, the construction manager,
and the architect during the construction. This will allow
swift action on change orders, scheduling issues and payment
approvals. The construction management and architectural
firms that are retained for the project should be committed
to dedicating sufficient numbers of their staff to the project.
During construction, all of the typical construction management
techniques should be utilized. Regular job meetings should
be held with all contractors and the architect present.
A critical path method (CPM) schedule should be maintained.
Coordination meetings should be held to coordinate the work
of separate prime or sub contractors. A daily logbook should
be maintained. Submittals should be required for all building
components needing architect approval.
When the construction has been substantially completed,
project closeout should begin. This includes completing
punch list items and obtaining warranties and certifications
from the contractors. Since the project was likely completed
in a rapid manner, special attention should be given to
making sure that all prime contractors execute an “affidavit
of payment of debts and claims” and all subcontractors
execute a “release of liens.” A final accounting
of the project expenditures should be prepared for the insurance
carrier. After all of this is complete, the building owner
will be asked to sign a final “proof of loss”
affidavit.
Conclusion
By following these suggestions, building owners can transform
a difficult and bleak situation into a successful project.
While building occupants will not blame the facilities department
for an unforeseeable tragedy, they will look to the facilities
department for answers if the recovery is not swift, not
of high quality and does not represent a suitable replacement
of what was lost. Building owners cannot be expected to
manage a large, fast-tracked reconstruction and remediation
project while continuing to care for their typical duties.
The professional assistance described in this article is
vital to a successful project.
A successful recovery from disaster allows the building
to return to full use in a timely manner. It allows the
insurance company to close their books and proceed with
litigation against any liable parties. And, it allows the
facilities manager to enjoy a reputation as a quick-acting,
efficient administrator.
FMJ
About the authors: Scott
Baird is a facility advisor and project executive with JMOA
Engineering, PC in Hawthorne, N.Y., USA. JMOA Engineering
is a construction management firm that specializes in K-12
construction and facility management. In addition to managing
more than $800 million in school construction projects,
JMOA Engineering has managed disaster recovery projects
for numerous school districts. Baird is currently managing
a $20 million capital improvements project in Somers, N.Y.,
USA, a $40 million capital improvements project in Cornwall,
N.Y., USA, and disaster recovery projects in Bedford and
Somers, N.Y., USA.
|